Key takeaways
- Risposte Turismo's Italian Cruise Watch, presented in Livorno on 23 October 2026, puts planned investment in Italian cruise ports for 2027-2029 at over €1.05 billion; the figure is a survey of port plans and records no spending (RT release as reprinted by il Nautilus).
- The four named categories (cruise infrastructure €339.7M, refuelling and alternative fuels €219.5M, new terminals €214.3M, dredging €205.8M) sum to €979.3 million, or 93.2% of the total by their published shares, leaving about €71-73 million unlabelled (our arithmetic on the RT figures as reported by il Nautilus).
- The regional split (Adriatic-Ionian €500M, Islands €321.3M, North Tyrrhenian €177.9M, Centre-South Tyrrhenian €53.2M) sums to €1,052.4 million, so the regions account for the whole total and the categories do not (our arithmetic).
- The release text reprinted by il Nautilus does not mention shore power, cold ironing or OPS; its only energy line is "rifornimenti e carburanti alternativi", and its content is not defined (il Nautilus reprint and Baird Maritime, 26 October 2026, checked 8 November 2026).
- EU Regulation 2023/1804 (AFIR), Article 9, requires TEN-T maritime ports above set call thresholds to supply shore power for at least 90% of calls by passenger ships over 5,000 GT by 31 December 2029 (EUR-Lex).
- EU Regulation 2023/1805 (FuelEU Maritime), Article 6, requires container and passenger ships at berth in those ports to connect to shore power from 1 January 2030, with eight listed exceptions, including stays under two hours (EUR-Lex).
- The headline totals of successive RT editions fell from about €1.6 billion (2024-2026) to over €1 billion (2026-2028) to over €1.05 billion (2027-2029), but the category labels changed between editions, so the splits cannot be compared line by line (RT 2023 release; Shipping Italy 2025; il Nautilus 2026).
- As of the latest dated reports found, Savona's cruise-terminal shore-power plant was completed on 21 July 2026 without an operator, Genoa's cruise berths were due for first tests in the second half of 2026, and Civitavecchia's €81 million project was still described in the future tense in March 2026 (Ports of Genoa; Shipping Italy; Italpress).
Italian cruise ports say they will invest more than €1.05 billion between 2027 and 2029. The four spending lines published with that figure add up to €979.3 million, and none of them is called shore power.
The figure comes from the Italian Cruise Watch, a survey by the Venice-based research firm Risposte Turismo, presented at the Italian Cruise Day in Livorno on 23 October 2026. It collects what port authorities plan to spend over the next three years. The release, as reprinted by il Nautilus, gives four categories with amounts and shares, a split across four stretches of coast and a list of eight new terminals. It gives no port count for the survey, no amount for any single port and no definition of what each category contains.
The gaps matter because European law now has a date. By 31 December 2029, the last day of the plan, busy EU ports on the TEN-T network must be able to supply cold ironing, or shore power, to at least 90% of passenger ship calls. From the next morning, ships at berth there must plug in, with limited exceptions. Italy funds shore power through a separate national programme, measured in separate figures. A reader of the €1.05 billion cannot tell how much of it, if any, pays for the cables the law requires.
What the €1.05 billion is, and what it is not
Risposte Turismo describes the total in two ways. The headline says over €1 billion. Francesco di Cesare, the firm's president, speaks of over €1.05 billion planned for 2027-2029. Both phrasings come from the same release text reprinted by il Nautilus, and Baird Maritime reported €1.05 billion on 26 October 2026.
The four named categories are specific. Infrastructure supporting cruising takes €339.7 million, or 32.3%. The release lists the kind of work it means: new or longer quays, mooring dolphins, new bollards, road surfaces, lighting and signage. Refuelling and alternative fuels take €219.5 million, or 20.9%. New cruise terminals take €214.3 million, or 20.4%, and the release adds that the figure rises to almost €270 million if renewals of existing terminals are counted. Dredging and seabed excavation take €205.8 million, or 19.6%.
Those four lines sum to €979.3 million. Their published shares sum to 93.2%. Divide each amount by its share and the implied base is about €1,050 million every time, which fits the over €1.05 billion in the quote. On that base, about €70.7 million, or 6.7%, has no label. Neither il Nautilus's reprint nor Baird Maritime's report names a fifth category, and the release does not say what the remainder covers.
The regional split behaves differently. The Adriatic-Ionian area gets €500 million, the Islands €321.3 million, the North Tyrrhenian €177.9 million and the Centre-South Tyrrhenian €53.2 million. These sum to €1,052.4 million, and their published shares sum to 99.96%. So the regions account for the whole total, while the categories account for about 93% of it. On the €1,052.4 million base the unlabelled amount is €73.1 million, or 6.9%, and the four categories are 93.1%. This article uses the €1,050 million base for category shares and the €1,052.4 million sum for regional shares, as the release's own percentages imply.
Reports of the release did not all present the terminals the same way. Baird Maritime gave percentages for three lines and put passenger terminals at almost €270 million including refurbishment, without a share.
Our own earlier Italy cruise statistics article reported the same four categories at 93.2% with about €73 million unitemized. Both numbers hold, on different bases: 93.2% is the sum of the published shares, and €73 million is the gap to the regional total.
| Group | Line | Amount (€M) | Share (%) |
|---|---|---|---|
| By category | Infrastructure supporting cruising (quays, dolphins, bollards, roads, lighting) | 339.7 | 32.3 |
| By category | Refuelling and alternative fuels | 219.5 | 20.9 |
| By category | New cruise terminals | 214.3 | 20.4 |
| By category | Dredging and seabed excavation | 205.8 | 19.6 |
| By category | Sum of the four named categories (our arithmetic) | 979.3 | 93.2 |
| By category | Unlabelled remainder on a €1,050M base (our arithmetic) | 70.7 | 6.7 |
| By category | Headline total (RT: over €1.05bn) | 1050 | 100 |
| By area | Adriatic-Ionian | 500 | 47.5 |
| By area | Islands | 321.3 | 30.5 |
| By area | North Tyrrhenian | 177.9 | 16.9 |
| By area | Centre-South Tyrrhenian | 53.2 | 5.06 |
| By area | Sum of the four areas (our arithmetic) | 1052.4 | 99.96 |
Three editions, three totals, no matching categories
The Italian Cruise Watch is an annual exercise, and each edition publishes a fresh three-year plan. Lined up, the headlines look like a decline. The 2023 edition, released on 16 October 2023 before the Cruise Day in Taranto, put investment for 2024-2026 at about €1.6 billion. The 2025 edition, reported by Shipping Italy on 24 October 2025, said investment for 2026-2028 would exceed €1 billion. The 2026 edition says over €1.05 billion for 2027-2029.
On paper the 2027-2029 total is about 34% below the 2024-2026 one. That is our arithmetic on two headline numbers, and it should not be read as a cut. The windows overlap: 2026 sits in the first plan and the second, 2027 and 2028 in the second and the third. Projects move from one plan to the next as they slip or finish. The sources do not list the ports surveyed in any edition, so nobody outside the survey can tell whether the samples match.
The categories changed too. The 2023 release split the €1.6 billion into new terminals at 32.6% (almost €530 million), preparing ports for alternative refuelling and energy supply at the quay at 26.7% (about €430 million), and other cruise infrastructure at over 20% (€330 million). Those three lines come to about €1.29 billion, roughly 81% of the total. Dredging had no line of its own. The 2025 edition, as reported, gave no category split at all. The 2026 edition has four lines, and dredging is one of them.
The label of the energy line is the most important change. In 2023 Risposte Turismo wrote of alternative refuelling "e agli approvvigionamenti energetici in banchina", energy supply at the quay, which is shore power in plain terms. In 2026 the line reads "rifornimenti e carburanti alternativi", refuelling and alternative fuels, with no mention of the quay. The share fell from 26.7% to 20.9%. Because the wording changed, the two shares measure different things, and the drop cannot be read as less money for shore power.
Two other series often sit next to these totals and belong to different questions. A pre-event report in Quality Travel said €860 million had been invested in 2024-2026, from early Italian Cruise Watch figures, with no breakdown. Setting that against the €1.6 billion planned for the same years would suggest a shortfall, but the scopes are not shown to match. The Adriatic Sea Forum, organized by Assoporti and Risposte Turismo according to Shipping Italy (27 June 2026), a report not reopened for this article, publishes totals for Adriatic ports only. In June 2026 it reported over €843 million for 2027-2030, of which €573 million was for cruise and ferry traffic and €270 million for leisure boating, according to Shipping Italy. Those figures cannot be added to or subtracted from the national plan.
The ministry has its own number. In October 2025 Deputy Minister Rixi said, as reported by Teleborsa, that there were over €335 million of dedicated works, more than €312 million of them funded directly by the transport ministry, across twenty projects. That is a ministerial statement about public funding, and it is not part of the Risposte Turismo survey.
| Edition | Plan period | Headline total (€M) | Source | Source status | Comparability |
|---|---|---|---|---|---|
| RT, October 2023 (Taranto) | 2024-2026 | 1600 | RT press release, 16 Oct 2023 | Primary, opened | Three lines: new terminals 32.6%, alternative refuelling and quay energy supply 26.7%, other infrastructure over 20%; no dredging line |
| RT, October 2024 | 2025-2027 | Not found | Not found | National total not found in any source searched | |
| RT, October 2025 | 2026-2028 | 1000 | Shipping Italy, 24 Oct 2025 | Press, opened | Reported as over €1bn; no category split; eight terminals by 2028 for about €190M |
| RT, October 2026 (Livorno) | 2027-2029 | 1050 | il Nautilus reprint, 23 Oct 2026 | Press, opened | Over €1.05bn; four lines summing to €979.3M; energy line no longer mentions the quay |
| Adriatic Sea Forum, June 2026 (Adriatic only) | 2027-2030 | 843 | Shipping Italy, 27 Jun 2026 | Press, not reopened | Adriatic ports only, four-year window, includes ferry and leisure boating; not comparable with national totals |
Cold ironing: the EU deadline the plan does not name
Cold ironing means plugging a ship into the port's electricity grid so it can switch off its diesel generators at berth. Cruise ships need power for their hotel services while they are in port. EU law calls the technology shore-side electricity supply, and two regulations adopted in 2023 set its timetable.
The first is the alternative fuels infrastructure regulation, known as AFIR, Regulation (EU) 2023/1804. Its Article 9 obliges member states to ensure, by 31 December 2029, that core and comprehensive TEN-T maritime ports supply shore power for at least 90% of calls by the ships it covers. For cruise ships, the rule applies to passenger ships above 5,000 gross tonnes in ports that average more than 25 such calls a year over three years. Ro-ro passenger ships and high-speed craft count from 40 calls, and container ships above 5,000 tonnes from 100. Ports on islands that are not directly connected to the mainland grid are exempt until that connection is built, or until enough local non-fossil electricity exists. Which Italian island ports qualify for the exemption was not examined for this article.
The second is FuelEU Maritime, Regulation (EU) 2023/1805. Its Article 6 turns the port obligation into a ship obligation. From 1 January 2030, passenger and container ships moored in ports covered by AFIR Article 9 must connect to shore power and use it for all their electricity needs at berth. From 1 January 2035, the same rule applies in any other port where shore power is available at the quay. Article 6(5) lists eight exceptions, including stays under two hours, ships using approved zero-emission technology, quays with no connection point, a risk to grid stability and equipment that is not compatible.
The 2027-2029 plan ends on the day AFIR's deadline falls. The release does not mention shore power, cold ironing or onshore power supply anywhere in the text reprinted by il Nautilus. Risposte Turismo's own Speciale Crociere 2026, published in March, says only that numerous ports plan to activate onshore power supply between 2026 and 2028, with no amounts and no list of ports.
The money for shore power runs through a national programme funded largely by the EU recovery plan, the PNRR, and its national complement. Its size depends on who is counting. Eunews reported in February 2025 that the PNRR set aside €400 million for cold ironing. Liguori, the transport ministry's director general for ports, told il Nordest that Italy would be first in the world with over €800 million spent, and Economia del Mare reported on 12 June 2026 that he described about €800 million of EU funds for 52 interventions and over 740 megawatts. SRM, the research centre of the Intesa Sanpaolo group, put planned cold-ironing works in Italian ports at €988 million, with €843 million already allocated, on a page last updated on 5 June 2026. A figure of €700 million also circulates. No source found for this article supports it as a euro amount.
Separately, the European Commission approved a €570 million Italian scheme in 2024 to encourage ships to use shore power, running until 31 December 2033, according to Ports Europe. The part of the report available does not describe how the aid works, and the scheme is separate from the money for building plants. None of these national figures is limited to cruise ports, since they also cover ferry and container berths, and none can be mapped onto the Risposte Turismo fuels line.
Port by port, the picture is uneven. Civitavecchia, Rome's cruise port and Italy's busiest, started building in February 2025: €81 million of PNRR money for nine berths, three of them for large cruise ships and two multipurpose, with completion planned by June 2026, according to eunews. In March 2026 the port authority's president, Latrofa, still spoke of the project in the future tense, as reported by Italpress. No report of its start of operation was found.
In Liguria, a ministry decree moved the €32 million of PNRR funds set aside for Genoa's ferry berths onto the cruise-berth projects of Genoa and Savona, which had been financed with €29.4 million in 2020 and had grown to about €32 million with extra costs, Shipping Italy reported on 19 June 2026. First tests on Genoa's cruise berths were expected in the second half of 2026. The ferry project in Genoa, originally due by the end of 2026, had not reached tender and will not be ready before 2028, the port authority said. On 21 July 2026 the authority announced that the Savona cruise-terminal plant was complete and would now move to the assignment of its management. Our Genoa and Savona homeport coast article covers the traffic these berths serve.
La Spezia connected MSC Seaview to its Molo Garibaldi system in a commissioning test in October 2025, Shipping Italy reported, with 10 megawatts available and a contract of just over €7 million for the transformer station. A second test with Costa Toscana followed in December 2025, ahead of planned operational use the next season, according to Ports Europe. A 2026 report of regular service was not found. Press reports from 2025 and May 2026 on Venice, Naples, Trieste and Salerno describe works at design or construction stage, or a plant without an operating framework. Those reports were not reopened for this article.
| Port | Project | Amount (€M) | Status and date | Source type | Verification |
|---|---|---|---|---|---|
| Civitavecchia | Nine electrified berths (3 large cruise, 2 multipurpose, 4 ro-ro/ro-pax), PNRR | 81 | Works began Feb 2025, completion planned June 2026; described as future work in March 2026; operation not found | Press (eunews; Italpress) | Press only |
| Genoa | Cruise berths at Stazioni Marittime; joint Genoa-Savona cruise projects, PNRR | 32 | First tests expected H2 2026 (report of 19 June 2026) | Press (Shipping Italy) | Press only |
| Savona | Cruise terminal substation and quay connections | Works completed 21 July 2026; operator not yet assigned | Port authority news (Ports of Genoa) | Verified (primary) | |
| Genoa (ferries) | Ferry quay electrification (its €32M PNRR moved to the cruise projects) | Not tendered; not before 2028 (report of 19 June 2026) | Press (Shipping Italy) | Press only | |
| La Spezia | Molo Garibaldi, transformer station contract, 10 MW available | 7 | Test connections Oct and Dec 2025; operational use planned for 2026 season; regular service not confirmed | Press (Shipping Italy; Ports Europe) | Press only |
| Venice (Marghera) | Electrification of new Canale Nord cruise berths | 18.5 | Contract reported April 2025; full operation planned for 2028 season | Press (Shipping Italy, Apr 2025) | Not reopened |
| Naples | Shore power needs a new primary substation | No shore power operating; grid and heritage constraints (report of May 2026) | Press (Shipping Italy, May 2026) | Not reopened | |
| Trieste | Electrified quays | Infrastructure available, no clear operating framework (report of May 2026) | Press (Shipping Italy, May 2026) | Not reopened |
New terminals and dredging: three numbers for the same buildings
The terminal list is the most concrete part of the release. Ravenna, Bari, Messina, Taranto and Brindisi are due to open new cruise terminals in 2027. Venezia-Marghera Canale Nord and Ancona follow in 2028, and La Spezia in 2029. Four of the eight replace existing buildings. The release puts the eight at €165 million.
That figure does not match the category table, where new terminals take €214.3 million, or almost €270 million with renewals. The gap between €214.3 million and €165 million is €49.3 million, by our arithmetic. The release offers no explanation, and the reprints do not attempt one. The two figures may count different things, such as works outside the eight named buildings, but no source says so, and this article does not guess.
The list itself has changed in a year. The 2025 edition promised eight new terminals by 2028 for about €190 million, naming Ravenna, Bari, Palermo, Messina, Ancona, La Spezia, Venice and Catania, according to Shipping Italy. In the 2026 list Palermo and Catania are gone, Taranto and Brindisi have joined, and La Spezia has moved to 2029. Neither release explains the changes.
Venice Marghera is the terminal with the clearest public trail. After big ships were barred from the Giudecca Canal, the port authority planned a new terminal on the Canale Nord in the industrial port. Shipping Italy reported in April 2025 that the land, about €16 million, had been bought, that an electrification contract was worth €18.5 million, and that works of over €67 million were at design stage, with two quays up to 300 metres and full operation planned for the 2028 season. The June 2026 Adriatic report put the two cruise berths at €72 million. Those figures come from earlier press reports and were not reopened here. Practical advice for the city is in the Venice travel guide, and the background is in Venice cruises five years after the big-ship ban.
Dredging takes €205.8 million, almost a fifth of the plan, more than the €165 million for the eight named terminals, though less than the €214.3 million terminals line. Dredging deepens channels and berths so that larger ships can enter. The release gives no port breakdown for it, and no source checked names which harbours will be dredged. The infrastructure line, the largest at €339.7 million, is equally unspecified by port.
Money by area, passengers by port
The regional split puts nearly half of the money in the Adriatic and Ionian seas. That area gets €500 million, or 47.5%. The Islands follow with €321.3 million, or 30.5%. The North Tyrrhenian gets €177.9 million, or 16.9%, and the Centre-South Tyrrhenian gets €53.2 million, or 5.06%.
The same release forecasts traffic that moves the other way in places. It expects the Islands to grow by 7.9% in 2027 and the Adriatic-Ionian area to dip by 0.7%. Risposte Turismo itself notes that the Adriatic-Ionian area will draw the largest share of investment despite a slight contraction in traffic. Part of the explanation is visible in the terminal list. Six of the eight new terminals, in Ravenna, Bari, Taranto, Brindisi, Venice and Ancona, are on the Adriatic or Ionian coast.
The ports that move the most passengers are elsewhere. For 2027 the release forecasts 3.8 million passenger movements and 990 calls at Civitavecchia, about 1.95 million at Naples, about 1.6 million at Genoa, over 1.2 million at Palermo and 845,000 at La Spezia. Civitavecchia and Naples together come to about 5.75 million, roughly 36% of the 16 million national forecast, by our arithmetic. Both sit on the central and southern Tyrrhenian coast, the area with the smallest investment share. The articles checked do not list which ports Risposte Turismo assigns to each area, so this reading of the map is ours.
The comparison has limits. The investment split is three years of planned euros by area. The traffic figures are one year of forecast passenger movements by port, and a passenger who starts or ends a cruise counts twice, once on boarding and once on leaving. A port can also carry its big projects outside the survey window. Civitavecchia's €81 million shore-power project, for instance, started in 2025 and was due to finish in 2026, before the 2027-2029 plan begins. The contrast raises a question about where capacity is being added. It does not show that any port is underfunded.
For the busiest ports the practical side is in the Rome travel guide, which covers Civitavecchia transfers, in the Naples travel guide, and in the Naples cruise port record and 2027 rebound.
What nobody measures
The Italian Cruise Watch is the only national source that tries to add up planned cruise-port investment, and it publishes its totals every October. What it does not publish is just as consistent. There is no list of the ports in the investment survey, no amount for any single port and no definition of the four categories. The 2027 traffic forecast is drawn from over 50 ports covering 92% of passengers and calls, but the release gives no matching sample description for the investment figures.
Nobody publishes a comparison of plans with spending. Each edition rolls three years forward, so a project that slips simply reappears in the next plan. The only spending figure found, €860 million invested in 2024-2026, came without a breakdown in a pre-event article and cannot be tested against the €1.6 billion planned for those years.
Shore power is measured even less well. There is no official national list of which cruise berths can supply electricity today, which are in testing, and which are waiting for an operator. The ministry, the recovery plan and a bank research centre each give a different total for the programme. Inside the cruise plan, the energy line changed its label between editions and no longer says whether it covers the quay.
The effects of all this spending are not measured either. No source checked reports how many ship calls actually used shore power, how much was spent ashore per cruise passenger, or how new terminals changed traffic at the ports that built them. Our Italy cruise statistics article found the same pattern in the traffic data, where forecasts and totals are plentiful and outcomes are scarce.
What this means for travelers, businesses and analysts
Travelers booking cruises calling in Italy in 2027 and 2028 can expect building work at several ports, with new terminals due at Ravenna, Bari, Messina, Taranto and Brindisi in 2027 and at Venice Marghera and Ancona in 2028. Turnaround passengers at those ports should check which terminal their line uses before arranging transfers. Shore power will not be universal by then. A ship running its engines at berth in 2027 or 2028 is not breaching the EU shore-power obligation, which for ships starts on 1 January 2030.
Tourism businesses and investors should treat the €1.05 billion as a statement of intent from port authorities, with no contracts behind it in the published data. The terminal list has already shifted once in a year, with Palermo and Catania dropped and La Spezia pushed to 2029, and businesses planning around a new terminal should follow the port authority's own tender and works announcements. Shore power is the clearest regulatory deadline. The operator decision pending at Savona (port authority, July 2026), and the operating framework still unclear at Trieste in a May 2026 press report, will show how the plants are run and charged. The €570 million state aid scheme to 2033 is designed to encourage ships to use shore power.
Journalists and analysts can cite these figures with their sources: over €1.05 billion planned for 2027-2029 (Risposte Turismo, October 2026); four named categories totalling €979.3 million; Adriatic-Ionian €500 million, or 47.5%; eight new terminals for €165 million; about €1.6 billion planned for 2024-2026 in the 2023 edition; the AFIR shore-power deadline of 31 December 2029; and the FuelEU at-berth obligation from 1 January 2030. They should not repeat that the €219.5 million fuels line is shore power, that Italy has a €700 million cold-ironing programme, that AFIR's deadline is 1 January 2030, that the categories sum to the total, or that the €165 million is the new-terminals line. National cold-ironing totals of €400 million, over €800 million and €988 million should always carry their source and date.
Data & sources
Period covered: Planned port investment 2027-2029 (Italian Cruise Watch, published 23 October 2026)
- Regulation (EU) 2023/1804 (AFIR), EUR-Lex · Alternative fuels infrastructure regulation. Article 9 sets shore-side electricity targets for TEN-T maritime ports (31 December 2029, 90% of calls, call thresholds, island exemption). Primary, opened. Accessed 8 Nov 2026.
- Regulation (EU) 2023/1805 (FuelEU Maritime), EUR-Lex · Article 6 obliges ships at berth to use shore power from 1 January 2030 in AFIR Article 9 ports and from 1 January 2035 elsewhere where available; Article 6(5) lists eight exceptions. Primary, opened. Accessed 8 Nov 2026.
- Risposte Turismo, Italian Cruise Watch 2026 release, as reprinted by il Nautilus (23 October 2026) · Release text from the Italian Cruise Day in Livorno: over €1.05bn planned 2027-2029, four categories, regional split, eight new terminals, 2027 traffic forecast and sample. Press reprint, opened; the release on risposteturismo.it was not opened. Accessed 8 Nov 2026.
- Risposte Turismo press release, Italian Cruise Day Taranto (16 October 2023), hosted by Assoporti · The 2024-2026 edition: about €1.6bn, 32.6% new terminals, 26.7% alternative refuelling and energy supply at the quay, over 20% other infrastructure; 12.9M passengers expected in 2023. Primary, opened. Accessed 8 Nov 2026.
- Shipping Italy, 2026-2028 edition report (24 October 2025) · Over €1bn planned for 2026-2028, eight new terminals by 2028 for about €190M, 15.4M passenger forecast for 2026, 5,680 calls. Press, opened. Accessed 8 Nov 2026.
- Risposte Turismo, Speciale Crociere 2026 (PDF) · 2025 actuals (14,742,938 passenger movements, 5,696 calls, 62 ports), definition of passenger movements (embarkations, disembarkations and transits) and a statement that numerous ports plan to activate OPS between 2026 and 2028, with no amounts. Primary, opened during research on 8 November 2026; not reopened by the writer. Accessed 8 Nov 2026.
- Ports of Genoa (AdSP del Mar Ligure Occidentale), Savona cold ironing completed (21 July 2026) · Port authority news: shore-power works at the Savona cruise terminal completed, management to be assigned. Primary, opened. Accessed 8 Nov 2026.
- Shipping Italy, Genoa cold ironing funds (19 June 2026) · €32M PNRR moved to the Genoa and Savona cruise-berth projects (€29.4M under a 2020 decree, about €32M with extra costs); first tests on Genoa cruise berths expected in the second half of 2026; ferry project not before 2028. Press, opened. Accessed 8 Nov 2026.
Methodology
This article draws on the text of Regulation (EU) 2023/1804 (AFIR) and Regulation (EU) 2023/1805 (FuelEU Maritime) on EUR-Lex; the Risposte Turismo Italian Cruise Watch 2026 release as reprinted by il Nautilus on 23 October 2026; the Risposte Turismo press release of 16 October 2023, hosted by Assoporti; Shipping Italy's report of 24 October 2025 on the 2026-2028 edition; the Risposte Turismo Speciale Crociere 2026; port-authority news from Ports of Genoa; and reports from Baird Maritime, Shipping Italy, eunews, Italpress, Ports Europe, il Nordest and Intesa Sanpaolo's SRM research page, all opened on 8 November 2026. Figures attributed to Quality Travel, Teleborsa, Economia del Mare and to Shipping Italy's reports of April 2025, May 2026 and 27 June 2026 come from earlier reporting and were not reopened for this article.
Limitations: (1) The 2026 release was read through a press reprint; the original on risposteturismo.it was not opened. (2) Investment figures are plans that ports report to a private research firm, with no audit and no follow-up on spending. (3) The survey's port list, category definitions and area boundaries are not published in the sources read. (4) Port-by-port shore-power status comes mostly from press reports dated between March and July 2026 and may have changed since. (5) Several figures in our research brief (Venice Marghera amounts, Naples and Trieste status, the 52 interventions and 740 MW of the national programme, the ministry's €335 million statement of October 2025) were taken from press reports cited in earlier reporting and not reopened for this article; they are attributed to the outlet that reported them. (6) The EU Mediterranean emission control area and AFIR's general application date were not checked against primary text and are not used.
Where sources disagree, both values are given with their source and date. Our own sums, differences and shares are labelled as our arithmetic and state their base. Claims that could not be found in any opened source, including some that circulate in trade press, are listed in the disclaimer and are not used as facts. A figure that a newspaper reports from Risposte Turismo is described as an RT figure as reported by that outlet.
Notes on the data
There is no per-port breakdown of the €1.05 billion, no published count of the ports in the investment survey, no definition of its categories, no national register of cruise-port spending, no comparison of planned with spent money, no national total found for the 2024 edition and no official list of Italian cruise berths with shore power in regular operation. Several figures are contested. The total is over €1.05 billion, while the four named categories sum to €979.3 million and the regional split to €1,052.4 million. New terminals appear as €214.3 million in the category table, about €270 million including renewals and €165 million for the eight named terminals. The national cold-ironing programme appears as €400 million of PNRR money (eunews, February 2025), over €800 million (MIT ports director general Liguori, as reported by il Nordest and Economia del Mare) and €988 million planned with €843 million allocated (SRM, Intesa Sanpaolo, June 2026). These claims failed verification or were mislabelled: that the €219.5 million line is shore power (the release text does not say so); a €700 million national cold-ironing figure (not found; 700 appears as megawatts in one report); that AFIR's shore-power deadline is 1 January 2030 (Article 9 says 31 December 2029; 1 January 2030 is the FuelEU date for ships); that the €1.05 billion sums from its four categories; and that the €165 million is the new-terminals line. Our earlier cruise statistics article's 93.2% is the sum of published shares; on the €1,052.4 million regional sum the four categories are 93.1%. The remainder (€70.7 to €73.1 million), the shares on stated bases, the 34% fall between headline totals and the 36% passenger share of Civitavecchia and Naples are derived figures. Investment totals are self-reported plans collected from ports; the 2027 traffic numbers are forecasts.
Frequently asked questions
How much will Italy invest in cruise ports in 2027-2029?
Risposte Turismo's Italian Cruise Watch puts planned investment at over €1.05 billion for 2027-2029, according to the release presented at the Italian Cruise Day in Livorno on 23 October 2026 and reprinted by il Nautilus. It is a survey of what port authorities plan to spend. No source published so far tracks how much of an earlier plan was actually spent.
Why don't the investment categories add up to €1.05 billion?
The release lists four categories: €339.7 million for cruise infrastructure, €219.5 million for refuelling and alternative fuels, €214.3 million for new terminals and €205.8 million for dredging (il Nautilus reprint). They sum to €979.3 million, 93.2% by their published shares. The remaining €71-73 million (our arithmetic) has no label in the il Nautilus reprint or the Baird Maritime report, and the release does not explain it.
What is cold ironing?
Cold ironing, also called shore power or onshore power supply (OPS), lets a ship at berth switch off its diesel generators and draw electricity from the port grid. EU Regulation 2023/1804 (AFIR) calls it shore-side electricity supply and sets targets for TEN-T maritime ports by 31 December 2029 (EUR-Lex).
When do cruise ships have to use shore power in EU ports?
Under FuelEU Maritime (Regulation 2023/1805, Article 6), passenger and container ships moored in ports covered by AFIR Article 9 must connect to shore power from 1 January 2030. In other ports the obligation applies from 1 January 2035 where shore power is available at the quay. Article 6(5) lists eight exceptions, including stays under two hours and quays with no connection point (EUR-Lex).
Does the €1.05 billion plan include shore power?
The 2026 release does not say. Its only energy line is "rifornimenti e carburanti alternativi" (€219.5 million, 20.9%), and neither the il Nautilus reprint nor Baird Maritime's report defines it. The 2023 edition's comparable line explicitly covered alternative refuelling and energy supply at the quay (RT release of 16 October 2023), but the 2026 label leaves the quay out, so the €219.5 million should not be described as shore power.
Which Italian cruise ports have shore power working?
No official national list was found. Press and port-authority reports show Savona's cruise-terminal plant completed on 21 July 2026 with no operator yet assigned (Ports of Genoa), first tests on Genoa's cruise berths planned for the second half of 2026 (Shipping Italy, 19 June 2026), and test connections at La Spezia's Molo Garibaldi in October and December 2025 (Shipping Italy; Ports Europe). Regular operation at any Italian cruise berth was not confirmed in the sources checked.
Which new cruise terminals will open in Italy by 2029?
The release lists eight: Ravenna, Bari, Messina, Taranto and Brindisi in 2027; Venezia-Marghera Canale Nord and Ancona in 2028; and La Spezia in 2029, four of them replacing existing buildings, for €165 million (il Nautilus reprint). The 2025 edition's list of eight terminals by 2028 named different ports, including Palermo and Catania (Shipping Italy, 24 October 2025).
Which part of Italy gets most of the cruise port money?
The Adriatic-Ionian area: €500 million, 47.5% of the total, ahead of the Islands (€321.3 million, 30.5%), the North Tyrrhenian (€177.9 million, 16.9%) and the Centre-South Tyrrhenian (€53.2 million, 5.06%), according to the release as reprinted by il Nautilus. The same release forecasts a 0.7% traffic dip in the Adriatic-Ionian area in 2027 and 7.9% growth in the Islands.
Is cruise port investment in Italy falling?
The headline totals are lower: about €1.6 billion for 2024-2026 in the 2023 edition (RT release, 16 October 2023), over €1 billion for 2026-2028 (Shipping Italy, 24 October 2025) and over €1.05 billion for 2027-2029. The windows overlap, the categories changed and the surveyed ports are not listed, so the change does not prove that ports are investing less.